| Conewago Municipal Authority Board Members | ||||
|---|---|---|---|---|
|
|
|
|
|
| Greg Hill | John Rochat | Joel Buckley | Ralph Luttrell | Norm Miller |
| chairman | vice-chair | secretary-treasurer | asst secretary | asst treasurer |
| term ends Jan 2014 | term ends Jan 2011 | term ends Jan 2015 | term ends Jan 2012 | term ends Jan 2013 |
| 5 members, 1 appointed by township supervisors every year for a 5 yr term. | ||||
| Usual meeting time is first Tuesday of Month at 7pm. | ||||
| Conewago Municipal Authority Appointed Officials | ||||
|---|---|---|---|---|
|
|
| ||
| Peter Henninger | Matt Cichy | Dolores Kuntz | ||
| Solicitor
Jones & Henninger | Engineer
Herbert, Rowland & Grubic | Recording Secretary | ||
| Conewago Municipal Authority
2009 Meeting Minutes | ||
|---|---|---|
| Jan 06, 2009 canceled | Feb 03, 2009 | Mar 03, 2009 canceled |
| Apr 07, 2009 | May 05, 2009 canceled | Jun 02, 2009 |
| Jul 07, 2009 canceled | Aug 04, 2009 canceled | Sep 01, 2009 canceled |
| Oct 06, 2009 canceled | Nov 10, 2009 | Dec 01, 2009 |
| 2005 - 2008 Meeting Minutes are in the Records Archive. | ||
| Conewago Municipal Authority
2010 Meeting Minutes | ||
|---|---|---|
| Jan 05, 2010 | Feb 02, 2010 canceled | Mar 02, 2010 canceled |
| Apr 06, 2010 canceled | May 04, 2010 | Jun 01, 2010 canceled |
| Jul 06, 2010 | Aug 03, 2010 | Sep 07, 2010 |
| Oct 05, 2010 | Nov 09, 2010 | Dec 07, 2010 |
| 2005 - 2009 Meeting Minutes are in the Records Archive. | ||
Phase II Sewer Information
Latest News: As this is written (March 9, 2007), construction has just begun with projected completion of the Phase II Sewer Extension in mid-2008. See Mar 07, 2007 CMA Press Release Construction of the Phase II Sewer Project is administered by Derry Township Municipal Authority, 670 Clearwater Road, Hershey, PA 17033-2453, phone 717.566.3237 extension 301, Mrs. Kim Bloom. Prior to sewer hook-up, Phase II residents must comply with the septic pumping requirements in place for the rest of the township. (Unofficially, if you received notice to pump in 2007, but are going to hook up to the sewer in 2008, I think it unlikely that the township will take enforcement action against you if you delay pumping until your sewer hookup.)
![]() Sewer Phase 2 Map |
|---|
Where's the sewer going? The township's Act 537 plan, (the so-called 5-10 year plan or Phase II) also calls for extending the sewer to Rt 743/Old Hershey Rd area. The plan includes most of Ridge Rd from Chestnut to Old Hershey. Most of Old Hershey north of Ridge Road. Round Top from Old Hershey to about 4103 Round Top. The west side of 743 from just above University Music to the Conewago School. As of March 2006 revisions, the east side of 743 goes to Adventure Sports and the Free Church parcel. (It may also extend to some businesses below Adventure Sports.)
When is it going to be here?
Phase II Sewer Area is moving from the design to the construction stage. Sewer construction began March 5, 2007 in the Jacob's Creek area. No firm schedule is available, but it may move to Ridge Road within a number of weeks.
Phase II Sewer Timeline
What will it cost?
The Conewago Municipal Authority submitted an application for funding assistance to PENNVEST on June 6, 2006. A funding award was made on July 18, 2006. Construction bids were received on November 6, 2006. Tentative agreement has been reached with DTMA on a Sewer Service agreement. Some adjustment may be made to the PennVest award prior to closing scheduled for January 17, 2007. Actual construction award should be made after that. Some changes were made to the PennVest financing due to lower than expected costs. Closing took place on March 1, 2007.
First you have the one-time hook-up costs. Start with a "tapping fee" of $6000. This represents only a portion of system construction costs. Add your cost to run the sewer to your house from the street, maybe another $3000. This will vary depending on how long the run is, and whether your inside plumbing needs to be modified. Your existing septic tank has to be filled in. If you need a grinder pump to go up hill, maybe another $___. There will be a credit of about $4400 for residences (not commercial) that will need grinder pumps.
Phase 2 tapping fees: From the March 6, 2007 CMA meeting: a $6000 tapping fee, $4400 residential grinder pump credit is expected.
Monthly fees. DTMA's current monthly fees are: The monthly sewer fee for users with wells will be $33.00 ($396.00/yr). For users with metered water, monthly fee will be $9.00 + $4.30 per 1000 gallons. These fees reflect the April 2007 5% rate increase. From the March 6, 2007 CMA meeting: The monthly costs for Phase II should be the same as Conewago Phase I and in Derry Township.
These are Conewago Township and Conewago Municipal Authority documents relating to the Phase II Sewer Plan. This is in order by date.
This document is also available for review at the township office.
It was largely prepared by the township engineer, Rettew Assoc.
It is rather lengthy and includes an asessment of the need for waste water treatment in the township.
It presents a number of alternate plans for meeting this need.
It incorporates both 0-5 and 5-10 year plans.
It includes written public comments and responses.
Act 537 Update July 2005
Public comment period ends Aug 24, 2005.
Scheduled for adoption at Sep 14, 2005 meeting
PENNVEST Loan and Grant
July 18, 2006
Pennvest Debt Ordinance, Mandatory Sewer Connection Ordinance, Conewago Township - Conewago Municipal Authority Sewer Service Agreement, Conewago Municipal Authority Rights-of-Way
November 08, 2006
| Nov 08, 2006 | Ord. 2006-3 | Pennvest (Sewer) Debt (Phase II) |
| Nov 08, 2006 | Ord. 2006-4 | Mandatory Sewer Connection (Phase II) |
| Nov 08, 2006 | Res. 2006-10 | Conewago Township - Conewago Municipal Authority Agreement |
| Nov 08, 2006 | Agreement | Conewago Township - Conewago Municipal Authority Agreement |
| Nov 08, 2006 | Res. 2006 11 | Conewago Municipal Authority Rights-of-Way |
Phase 2 Sewer Service Agreement and Lease Agreement among Conewago Township, Conewago Municipal Authority and Derry Township Municipal Authority; DTMA Rules, Rates and Regs
| Feb 10, 2007 | Sewer Service Agreement (Phase 2) |
| Feb 19, 2007 | Lease Agreement (Phase 2) |
| Mar 05, 2007 | DTMA Rules Rates and Regs |
| Apr 01, 2007 | DTMA Rates |
PENNVEST Loan and Grant (REVISED)
March 1, 2007
Mar 07, 2007 - CMA Press Release on Construction Start
|